Planning the install
Reading the documents, walking the site, receiving equipment and coordinating with other trades.
About 12 minutes
Most installation problems are planning problems that showed up late.
Read the documents first
Before day one, read the drawings (floor plans, elevations, signal flow, rack elevations), the scope of work and the equipment list. Note anything unclear and ask your project manager. Find out the site rules: access hours, badges, parking, where you can store material, and safety orientation.
Walk the site
A site walk checks the drawings against reality:
- Are the walls what the drawings say (stud, block, concrete, glass)?
- Is there backing or blocking where displays will mount?
- Are the pathways (conduit, back boxes, ceiling access) in place and the right size?
- Is power where it should be?
If reality doesn't match the design, stop and report it before you work around it. A quiet workaround becomes a dispute later.
Receive and stage equipment
Check deliveries against the order as soon as they arrive. Missing or damaged items found on delivery day can be replaced without slipping the schedule. Stage equipment by room, keep it secure, and keep boxes until you know you won't need to return anything.
Coordinate
AV work depends on other trades: electricians for power and conduit, carpenters for blocking, ceiling installers, IT for network ports. A kickoff meeting sets the schedule and who does what. Penetrations through fire-rated walls and floors must be approved and restored with a listed firestop system; never leave an open penetration.