AV infrastructure is built by other trades from your drawings. If it isn't in the drawings, it won't be in the building.

Pathways

  • Show conduit, back boxes, floor boxes and cable tray with sizes and routes.
  • Respect conduit fill (in the US, generally 40% for more than two cables) and plan for future cables.
  • Keep AV cabling separated from power and within cable length limits (for example 100 m for twisted pair).
  • Coordinate floor boxes with the furniture layout, electrical and low-voltage pathways.

Power

Give the electrical engineer the total load, circuits, receptacle types and locations, and any UPS, isolated ground or sequencing requirements.

Heat

Equipment heat (watts x 3.41 = BTU/hr) goes to the mechanical engineer so racks, closets and credenzas are cooled and ventilated.

Structure

Heavy displays, projectors, speakers, lifts and video walls need backing, blocking and supports coordinated with the architect and structural engineer, including seismic bracing where required.

Review it

Check the other trades' drawings against yours during design, and visit the site during construction. Pathways fixed on paper cost nothing; pathways fixed after drywall cost a lot.