Testing and commissioning control systems

Test plans, failure testing, combinable rooms, schedules and recording what you find.

About 12 minutes

Write a test plan

A test plan lists every function to check:

  • Every button and page on every panel.
  • Error conditions: a device unplugged, a network cable pulled, a device that takes too long.
  • Power loss recovery.
  • Scheduled events (morning start, evening all-off).
  • Every combination of a divisible room and the transitions between them.

Test failure on purpose

Disconnect a device and see what the user sees. A system that freezes because one projector is unplugged isn't finished.

Test schedules for real

Let a scheduled event trigger, or simulate the time, and confirm every room ends in the right state. Reading the code isn't testing.

Record bugs well

For each problem, write steps to reproduce, what happened, what should happen, and the fix. This turns commissioning into a record the client can trust and the next programmer can use.

Re-test after changes

Any change, however small, gets re-tested along with the functions that depend on it. Most "it was working yesterday" calls come from untested last-minute changes.